Jct MT 40 - South
US 93
Description
The Jct MT 40 – South project will overlay the existing roadway with new pavement, followed by a chip seal and fog seal. In addition, new pavement markings, signing, delineation, raised concrete median replacement, ADA curb ramp upgrades, guardrail and shoulder rumble strips will be included. The project is being developed to correct the rutting issues, and to extend the useful life of the highway. The project begins 0.5 miles north of the City of Kalispell (mile post 119.4), and ends at the intersection of US-93 and MT-40 (just south of the City of Whitefish, at mile post 125.5) on US-93 (N-5), in Flathead County.
As written by the source.
Timeline
Date not stated · first seen Nov 26, 2026 · MDT project status
MDT lists this project as planned: type rehabilitation, construction year 2027.
MDT active projects in Flathead County · Open the source document(opens in a new tab)